Here is the proposed schedule (according to the Williams' Gas website information) for construction:
| Preparation activities begin (removing trees and fences) | 07/08/10 |
| Pipeline taken out of service | 07/19/10 |
| Crews begin work at Five Mile Road | 07/20/10 |
| Crew 1 crosses Lawrence Road | 07/23/10 |
| Crew 1 crosses Ardmore Lane | 07/27/10 |
| Crew 2 begins work at Briar Cliff Lane | 07/28/10 |
| Crew 1 crosses Toni Rae Drive | 07/31/10 |
| Crew 1 crosses Gail Jean Lane | 08/11/10 |
| Crew 1 crosses Edna Lane | 08/15/10 |
| Crew 2 completes work | 08/13/10 |
| Crew 1 completes work | 08/16/10 |
| Pipeline returned to service | 08/27/10 |
| Final grading and cleanup | 09/10/10 |
| Crews demobilize and vacate area | 09/15/10 |