Road Closures July-August for Gas Pipeline.

Pipeline construction begins.

Here is the proposed schedule (according to the Williams' Gas website information) for construction:

Preparation activities begin (removing trees and fences) 07/08/10
Pipeline taken out of service 07/19/10
Crews begin work at Five Mile Road 07/20/10
Crew 1 crosses Lawrence Road 07/23/10
Crew 1 crosses Ardmore Lane 07/27/10
Crew 2 begins work at Briar Cliff Lane 07/28/10
Crew 1 crosses Toni Rae Drive 07/31/10
Crew 1 crosses Gail Jean Lane 08/11/10
Crew 1 crosses Edna Lane 08/15/10
Crew 2 completes work 08/13/10
Crew 1 completes work 08/16/10
Pipeline returned to service 08/27/10
Final grading and cleanup 09/10/10
Crews demobilize and vacate area 09/15/10

 

Please post any additional updates in the Forum and/or the development@northfivemile.com

email list.

 

 

Reference:

http://www.williams.com/spokanereplacement/default.aspx

 

 

 